latest news

Completed projects

Construction of Monze Correctional Service facility

The facility was constructed in Four (4) phases. The final phase of construction commenced in October 2014 and was fully completed in August, 2017.

On – going projects

Construction of correctional service facilities

The Ministry of Home Affairs is currently constructing two correctional service facilities in Mwembeshi under the Public Private Partnership. The Ministry successfully engaged two developers namely Mukuyu Ventures Limited and Saltech Enterprises Limited.

The Construction of the Correctional facility by Mukuyu Ventures Limited was commissioned on the 16th May, 2016 and is expected to be completed in 2018. The proposed facility under construction has been designed to have a bed capacity of 1800.

Progress on the project

Currently the developers have set out and are constructing the perimeter fences and all the proposed facilities within the facilities.

Photos of the construction of the facilities

constructions
homes

Construction of the ministry headquaters building blocks

The Ministry of Home Affairs engaged China Jiangxi Corporation Limited to construct two five storey and one four storey office blocks at Ridgeway area. Two of the five storey blocks have been built and are at 85% complete. The project began in August, 2012 the two office blocks are scheduled for completion in June, 2018.

Construction of boarder and immigration office blocks

The Ministry of Home Affairs through the Immigration department is currently constructing three office blocks in Nsumbu, Lukulu and Mwandi. The office blocks are currently at roof level.

monze
construction

Construction of housing for the security wings under the ministry

The Ministry engaged AVIC International Holding Corporation for the construction of Two Thousand Three Hundred and Fifty Housing Units (2,350) under Phase 1 for the four departments namely Zambia Police Service, Drug Enforcement Commission, Zambia Correctional Service and Immigration. The project was officially launched on the 27th October 2015 and came into effect on the 7th July, 2017.

Progress on the project

As at the end of 2017 a total of 195 housing units were completed. A total of 825 housing units are under construction.

Photos of the construction of the facility

offices
borser office